Diversity grouped from RERA project_type. Sell-through, completion %, delays and upcoming handovers
derived from total_units, units_sold, completion_percent,
proposed_completion & actual_completion across all merged promoter entities.
| Project | RERA Reg | Status | District | Area | Map | Website |
|---|---|---|---|---|---|---|
| ARCHEE ICON CITY | PCGRERA070718000497 |
Ongoing | Raipur | - | Map | Visit |
| govinda green | PCGRERA210921001268 |
New | Raipur | - | Map | - |
| Harshit Fortuna | PCGRERA230618000302 |
Ongoing | Raipur | - | Map | Visit |
| Harshit gold city | PCGRERA040123001580 |
New | Raipur | - | Map | Visit |
| Harshit Harmony | PCGRERA200618000241 |
Ongoing | Raipur | - | Map | Visit |
| HARSHIT HARMONY EXTENSION | PCGRERA191225002013 |
New | Raipur | - | Map | - |
| HARSHIT HARMONY PHASE -II | P3CGRERA161118000013 |
Completed | RAIPUR | - | Map | - |
| HARSHIT HARMONY PHASE -II | P3CGRERA161118000013 |
- | RAIPUR | - | Map | - |
| Harshit Icon City | PCGRERA050718000466 |
Ongoing | Raipur | - | Map | Visit |
| harshit landmark (phase-i, block -a&b) | PCGRERA160718000539 |
Ongoing | Raipur | - | Map | Visit |
| HARSHIT LANDMARK (PHASE-II, BLOCK- C & D) | PCGRERA270618000349 |
Ongoing | Raipur | - | Map | Visit |
| HARSHIT LANDMARK (PHASE-III, BLOCK -E & F) | PCGRERA270618000352 |
Ongoing | Raipur | - | Map | Visit |
| HARSHIT LANDMARK (PHASE-IV, BLOCK-G) | PCGRERA270618000348 |
Ongoing | Raipur | - | Map | Visit |
| HARSHIT NEO CITY | PCGRERA070718000496 |
Ongoing | Durg | - | Map | Visit |
| HARSHIT PLATINUM GREEN | PCGRERA201125001992 |
New | Durg | - | Map | - |
| HARSHIT URBAN CITY | PCGRERA250724001799 |
New | Raipur | - | Map | - |
| # | Complaint No. | Applicant | Section | Date | |
|---|---|---|---|---|---|
| 1 | SM-PRO-2023-02010 | CG-RERA | Section 62 | 15 Jan 2025 | |
| 2 | M-COM-2024-02537 | CG-RERA | Section 60 | 10 Jan 2025 | |
| 3 | M-PRO-2024-02589 | BHAVNA PATEL | - | 20 Dec 2024 | |
| 4 | SM-EXP-2024-02229 | CG-RERA | - | 03 Apr 2024 | |
| 5 | M-COM-2023-02040 | CG-RERA | - | 11 Mar 2024 | |
| 6 | M-PRO-2022-01705 | SMT DAYAVATI CHAUHAN | - | 23 Aug 2022 | |
| 7 | M-PRO-2021-01453 | SHWETA SAINI MOHANTY | - | 20 Jul 2021 | |
| 8 | M-COM-2019-00646 | CG-RERA | Section 17 | 25 Mar 2021 | |
| 9 | M-PRO-2019-00694 | (1) SMT. PARVATI GUPTA, (2) SHRI KANHAIYA PRASAD GUPTA, (3) SMT. SEEMA GUPTA | Section 31 | 05 Sep 2019 | |
| 10 | M-PRO-2019-00438 | SHRI NIRMAL SINGH RANDHAWA, S/O SHRI GURUBACHAN SINGH RANDHAWA | Section 31 | 30 May 2019 | |
| 11 | M-PRO-2019-00256 | SMT AMITA PANDEY, W/O SHRI ALOK PANDEY | Section 31 | 15 May 2019 | |
| 12 | M-PRO-2019-00255 | SMT SUDHA SHARMA W/O SHRI PRAVEEN KUMAR SHARMA | Section 31 | 15 May 2019 | |
| 13 | M-PRO-2018-00151 | SHRI D.R. SAHU S/O B.N. SAHU | Section 31 | 09 Jan 2019 | |
| 14 | M-PRO-2018-00057 | SHRI C RAMKUMAR NAIR S/O P RAJGOPAL NAIR | Section 18 | 05 Sep 2018 |
| Factor | How it's calculated | Raw Value | Score (0-100) | Weight | Weighted |
|---|---|---|---|---|---|
| Builder-Level RERA Compliance Score | 16 project(s): 9 Compliant(100), 6 Partial(50) | 80/100 |
80
|
60% | 48.0 |
| Orders & Violations | 9 order(s) under 5 distinct RERA section(s). Score = max(0, 100 - 5 x 4) = 80 | 5 section(s) |
80
|
40% | 32.0 |
| Complaints Filed | 9 complaint(s) total. Only complaints with actual orders affect the score (via "Orders & Violations" factor above). | 9 | Info only — not scored | ||
| Buyer Rating | Average buyer review rating across all projects by this builder. | No reviews | Info only — not scored | ||
| Order Details | |||||
| Weighted Sum / Total Weight | 100% | 80.0 | |||
| Final Normalized Score | 80/100 | ||||
Avg. Completion % = SUM(effective_completion) / COUNT(projects with completion_percent NOT NULL)
completion_percent = 100
while their registration_status is still Ongoing / New and no
actual_completion date is filed. Per RERA, a project is only formally complete when
status = Completed OR actual_completion is set. So we cap such projects at
99% for averaging. Capped rows below are marked
CAPPED.
seemankan1.projects.completion_percent · Excludes projects with NULL completion.
| Project | RERA | Status | Reported | Effective % |
|---|---|---|---|---|
| govinda green | PCGRERA210921001268 |
New | 100% | CAPPED 99% |
| Harshit Fortuna | PCGRERA230618000302 |
Ongoing | 100% | CAPPED 99% |
| Harshit gold city | PCGRERA040123001580 |
New | 100% | CAPPED 99% |
| Harshit Harmony | PCGRERA200618000241 |
Ongoing | 100% | CAPPED 99% |
| harshit landmark (phase-i, block -a&b) | PCGRERA160718000539 |
Ongoing | 100% | CAPPED 99% |
| HARSHIT LANDMARK (PHASE-II, BLOCK- C & D) | PCGRERA270618000349 |
Ongoing | 100% | CAPPED 99% |
| HARSHIT NEO CITY | PCGRERA070718000496 |
Ongoing | 100% | CAPPED 99% |
| HARSHIT URBAN CITY | PCGRERA250724001799 |
New | 100% | CAPPED 99% |
| ARCHEE ICON CITY | PCGRERA070718000497 |
Ongoing | 91% | 91% |
| HARSHIT LANDMARK (PHASE-IV, BLOCK-G) | PCGRERA270618000348 |
Ongoing | 80% | 80% |
| HARSHIT LANDMARK (PHASE-III, BLOCK -E & F) | PCGRERA270618000352 |
Ongoing | 69% | 69% |
| Harshit Icon City | PCGRERA050718000466 |
Ongoing | 62% | 62% |
| HARSHIT PLATINUM GREEN | PCGRERA201125001992 |
New | 21% | 21% |
| HARSHIT HARMONY EXTENSION | PCGRERA191225002013 |
New | 10% | 10% |
| SUM ÷ COUNT | 1,125 ÷ 14 = 80% | |||
proposed_completion < today (23 Apr 2026)registration_status ≠ Completed AND actual_completion is NULL/emptycompletion_percent is intentionally not used here because RERA developers
self-report 100% even while the project is still Ongoing. Only the formal status / actual completion
date proves the project is closed.
| Project | RERA | Status | Proposed Completion | Completion % | Days Overdue |
|---|---|---|---|---|---|
| Harshit Fortuna | PCGRERA230618000302 |
Ongoing | 31 Dec 2018 | 100% | 2,670 d |
| harshit landmark (phase-i, block -a&b) | PCGRERA160718000539 |
Ongoing | 30 Aug 2021 | 100% | 1,697 d |
| HARSHIT NEO CITY | PCGRERA070718000496 |
Ongoing | 28 Feb 2022 | 100% | 1,515 d |
| Harshit Harmony | PCGRERA200618000241 |
Ongoing | 28 Feb 2023 | 100% | 1,150 d |
| HARSHIT HARMONY PHASE -II | P3CGRERA161118000013 |
28 Feb 2023 | 0% | 1,150 d | |
| HARSHIT LANDMARK (PHASE-II, BLOCK- C & D) | PCGRERA270618000349 |
Ongoing | 29 Aug 2023 | 100% | 968 d |
| govinda green | PCGRERA210921001268 |
New | 15 Sep 2024 | 100% | 585 d |
registration_date ≥ 23 Apr 2023| Project | RERA | Status | Registered |
|---|---|---|---|
| HARSHIT HARMONY EXTENSION | PCGRERA191225002013 |
New | 19 Dec 2025 |
| HARSHIT PLATINUM GREEN | PCGRERA201125001992 |
New | 20 Nov 2025 |
| HARSHIT URBAN CITY | PCGRERA250724001799 |
New | 25 Jul 2024 |
proposed_completion between today and 23 Apr 2028actual_completion)| Project | RERA | Status | Proposed Completion | Completion % | Days Remaining |
|---|---|---|---|---|---|
| Harshit Icon City | PCGRERA050718000466 |
Ongoing | 14 Sep 2027 | 62% | 509 d |
| ARCHEE ICON CITY | PCGRERA070718000497 |
Ongoing | 09 Dec 2027 | 91% | 595 d |
| Harshit gold city | PCGRERA040123001580 |
New | 16 Dec 2027 | 100% | 602 d |
| HARSHIT LANDMARK (PHASE-IV, BLOCK-G) | PCGRERA270618000348 |
Ongoing | 15 Jan 2028 | 80% | 632 d |
| HARSHIT LANDMARK (PHASE-III, BLOCK -E & F) | PCGRERA270618000352 |
Ongoing | 31 Jan 2028 | 69% | 648 d |
| HARSHIT HARMONY EXTENSION | PCGRERA191225002013 |
New | 31 Mar 2028 | 10% | 708 d |