Diversity grouped from RERA project_type. Sell-through, completion %, delays and upcoming handovers
derived from total_units, units_sold, completion_percent,
proposed_completion & actual_completion across all merged promoter entities.
| Project | RERA Reg | Status | District | Area | Map | Website |
|---|---|---|---|---|---|---|
| NARAYANI GREENS phase - 1 | PCGRERA010923001663 |
New | Korba | - | Map | - |
| NARAYANI INCITY | PCGRERA280319000950 |
Ongoing | Korba | - | Map | Visit |
| narayani vihar | PCGRERA250419000963 |
Ongoing | Korba | - | Map | Visit |
| Factor | How it's calculated | Raw Value | Score (0-100) | Weight | Weighted |
|---|---|---|---|---|---|
| Builder-Level RERA Compliance Score | 3 project(s): 3 Compliant(100) | 100/100 |
100
|
60% | 60.0 |
| Complaints Filed | No complaints filed against this builder. | 0 | Info only — not scored | ||
| Buyer Rating | Average buyer review rating across all projects by this builder. | No reviews | Info only — not scored | ||
| Weighted Sum / Total Weight | 60% | 60.0 | |||
| Final Normalized Score | 100/100 | ||||
Avg. Completion % = SUM(effective_completion) / COUNT(projects with completion_percent NOT NULL)
completion_percent = 100
while their registration_status is still Ongoing / New and no
actual_completion date is filed. Per RERA, a project is only formally complete when
status = Completed OR actual_completion is set. So we cap such projects at
99% for averaging. Capped rows below are marked
CAPPED.
seemankan1.projects.completion_percent · Excludes projects with NULL completion.
| Project | RERA | Status | Reported | Effective % |
|---|---|---|---|---|
| narayani vihar | PCGRERA250419000963 |
Ongoing | 100% | CAPPED 99% |
| NARAYANI GREENS phase - 1 | PCGRERA010923001663 |
New | 17% | 17% |
| NARAYANI INCITY | PCGRERA280319000950 |
Ongoing | 2% | 2% |
| SUM ÷ COUNT | 118 ÷ 3 = 39% | |||
registration_date ≥ 27 Apr 2023| Project | RERA | Status | Registered |
|---|---|---|---|
| NARAYANI GREENS phase - 1 | PCGRERA010923001663 |
New | 01 Sep 2023 |
proposed_completion between today and 27 Apr 2028actual_completion)| Project | RERA | Status | Proposed Completion | Completion % | Days Remaining |
|---|---|---|---|---|---|
| NARAYANI INCITY | PCGRERA280319000950 |
Ongoing | 30 Sep 2026 | 2% | 156 d |
| narayani vihar | PCGRERA250419000963 |
Ongoing | 30 Sep 2026 | 100% | 156 d |
| NARAYANI GREENS phase - 1 | PCGRERA010923001663 |
New | 31 Mar 2028 | 17% | 704 d |