Diversity grouped from RERA project_type. Sell-through, completion %, delays and upcoming handovers
derived from total_units, units_sold, completion_percent,
proposed_completion & actual_completion across all merged promoter entities.
| Project | RERA Reg | Status | District | Area | Map | Website |
|---|---|---|---|---|---|---|
| SHRI SHYAM VATIKA | PCGRERA160524001776 |
New | Raigarh | - | Map | Visit |
| # | Complaint No. | Applicant | Section | Date | |
|---|---|---|---|---|---|
| 1 | M-COM-2025-03255 | CG-RERA | - | 30 Mar 2026 |
| Factor | How it's calculated | Raw Value | Score (0-100) | Weight | Weighted |
|---|---|---|---|---|---|
| Builder-Level RERA Compliance Score | 1 project(s): 1 Compliant(100) | 100/100 |
100
|
60% | 60.0 |
| Complaints Filed | No complaints filed against this builder. | 0 | Info only — not scored | ||
| Buyer Rating | Average buyer review rating across all projects by this builder. | No reviews | Info only — not scored | ||
| Weighted Sum / Total Weight | 60% | 60.0 | |||
| Final Normalized Score | 100/100 | ||||
Avg. Completion % = SUM(effective_completion) / COUNT(projects with completion_percent NOT NULL)
completion_percent = 100
while their registration_status is still Ongoing / New and no
actual_completion date is filed. Per RERA, a project is only formally complete when
status = Completed OR actual_completion is set. So we cap such projects at
99% for averaging. Capped rows below are marked
CAPPED.
seemankan1.projects.completion_percent · Excludes projects with NULL completion.
| Project | RERA | Status | Reported | Effective % |
|---|---|---|---|---|
| SHRI SHYAM VATIKA | PCGRERA160524001776 |
New | 75% | 75% |
| SUM ÷ COUNT | 75 ÷ 1 = 75% | |||
registration_date ≥ 23 Apr 2023| Project | RERA | Status | Registered |
|---|---|---|---|
| SHRI SHYAM VATIKA | PCGRERA160524001776 |
New | 16 May 2024 |