Diversity grouped from RERA project_type. Sell-through, completion %, delays and upcoming handovers
derived from total_units, units_sold, completion_percent,
proposed_completion & actual_completion across all merged promoter entities.
| Project | RERA Reg | Status | District | Area | Map | Website |
|---|---|---|---|---|---|---|
| sai city | PCGRERA150618000203 |
Ongoing | Bilaspur | - | Map | - |
| SHRI SAI CITY (PHASE-3) | PCGRERA281118000856 |
Ongoing | Durg | - | Map | Visit |
| # | Complaint No. | Applicant | Section | Date | |
|---|---|---|---|---|---|
| 1 | M-PRO-2021-01553 | SMT SHANTI DANI LAKRA | Section 18,Section 19 | 25 May 2022 | |
| 2 | M-ALL-2021-01316 | NEETU SINGH | Section 17,Section 18 | 31 Aug 2021 | |
| 3 | M-PRO-2019-00329 | SHRI PRITESH CHARVEY, S/O SHRI N.P. CHARVEY | Section 18,Section 17 | 15 Jan 2020 |
| Factor | How it's calculated | Raw Value | Score (0-100) | Weight | Weighted |
|---|---|---|---|---|---|
| Builder-Level RERA Compliance Score | 2 project(s): 2 Partial(50) | 50/100 |
50
|
60% | 30.0 |
| Orders & Violations | 3 order(s) under 3 distinct RERA section(s). Score = max(0, 100 - 3 x 4) = 88 | 3 section(s) |
88
|
40% | 35.2 |
| Complaints Filed | 3 complaint(s) total. Only complaints with actual orders affect the score (via "Orders & Violations" factor above). | 3 | Info only — not scored | ||
| Buyer Rating | Average buyer review rating across all projects by this builder. | No reviews | Info only — not scored | ||
| Order Details | |||||
| Weighted Sum / Total Weight | 100% | 65.2 | |||
| Final Normalized Score | 65/100 | ||||
Avg. Completion % = SUM(effective_completion) / COUNT(projects with completion_percent NOT NULL)
completion_percent = 100
while their registration_status is still Ongoing / New and no
actual_completion date is filed. Per RERA, a project is only formally complete when
status = Completed OR actual_completion is set. So we cap such projects at
99% for averaging. Capped rows below are marked
CAPPED.
seemankan1.projects.completion_percent · Excludes projects with NULL completion.
| Project | RERA | Status | Reported | Effective % |
|---|---|---|---|---|
| SHRI SAI CITY (PHASE-3) | PCGRERA281118000856 |
Ongoing | 100% | CAPPED 99% |
| sai city | PCGRERA150618000203 |
Ongoing | 90% | 90% |
| SUM ÷ COUNT | 189 ÷ 2 = 95% | |||
proposed_completion < today (25 Apr 2026)registration_status ≠ Completed AND actual_completion is NULL/emptycompletion_percent is intentionally not used here because RERA developers
self-report 100% even while the project is still Ongoing. Only the formal status / actual completion
date proves the project is closed.
| Project | RERA | Status | Proposed Completion | Completion % | Days Overdue |
|---|---|---|---|---|---|
| sai city | PCGRERA150618000203 |
Ongoing | 31 Dec 2019 | 90% | 2,307 d |
| SHRI SAI CITY (PHASE-3) | PCGRERA281118000856 |
Ongoing | 14 Aug 2024 | 100% | 619 d |