Diversity grouped from RERA project_type. Sell-through, completion %, delays and upcoming handovers
derived from total_units, units_sold, completion_percent,
proposed_completion & actual_completion across all merged promoter entities.
| Project | RERA Reg | Status | District | Area | Map | Website |
|---|---|---|---|---|---|---|
| sai city | PCGRERA150618000203 |
Ongoing | Bilaspur | - | Map | - |
| SHRI SAI CITY (PHASE-3) | PCGRERA281118000856 |
Ongoing | Durg | - | Map | Visit |
| # | Complaint No. | Applicant | Section | Date | |
|---|---|---|---|---|---|
| 1 | M-PRO-2021-01309 | SHRI VISHWAJIT PRADHAN, S/O SHRI GUNNIDHI PRADHAN | - | 28 Jul 2021 | |
| 2 | M-PRO-2020-01218 | SMT S. PADMAVATI, SHRI S.V. RAMAN | Section 17,Section 18 | 27 Jul 2021 | |
| 3 | M-PRO-2019-00935 | SHRI ANAND SHARMA, S/O LATE SHRI K.P. SHARMA | Section 18 | 31 Oct 2020 | |
| 4 | M-PRO-2019-00911 | SMT NIRMALA TIRKEY, SHRI ASIM HEMAM TIRKEY | Section 18 | 31 Oct 2020 | |
| 5 | M-PRO-2019-00856 | SHRI TRILOKINATH SHARMA, S/O SHRI SOHAN PRASAD SHARMA | Section 31 | 12 Oct 2020 | |
| 6 | M-PRO-2019-00875 | SHRI SHRIKANT SHARMA, S/O LATE SHRI SOHANG PRASAD SHARMA | Section 31 | 12 Oct 2020 | |
| 7 | M-PRO-2019-00859 | SHRI UTTAM KUMAR SONI, S/O SHRI SHYAM LAL SONI | Section 11 | 18 Aug 2020 | |
| 8 | M-PRO-2019-00858 | SHRI NARESH DEVIDAS MANEKAR, S/O LATE SHRI DEVIDAS MANEKAR | Section 11 | 18 Aug 2020 | |
| 9 | M-PRO-2019-00857 | SHRI PANNALAL CHOUDHARI, S/O SHRI GANESH CHOUDHARI | Section 11 | 18 Aug 2020 |
| Factor | How it's calculated | Raw Value | Score (0-100) | Weight | Weighted |
|---|---|---|---|---|---|
| Builder-Level RERA Compliance Score | 2 project(s): 2 Partial(50) | 50/100 |
50
|
60% | 30.0 |
| Orders & Violations | 8 order(s) under 4 distinct RERA section(s). Score = max(0, 100 - 4 x 4) = 84 | 4 section(s) |
84
|
40% | 33.6 |
| Complaints Filed | 8 complaint(s) total. Only complaints with actual orders affect the score (via "Orders & Violations" factor above). | 8 | Info only — not scored | ||
| Buyer Rating | Average buyer review rating across all projects by this builder. | No reviews | Info only — not scored | ||
| Order Details | |||||
| Weighted Sum / Total Weight | 100% | 63.6 | |||
| Final Normalized Score | 64/100 | ||||
Avg. Completion % = SUM(effective_completion) / COUNT(projects with completion_percent NOT NULL)
completion_percent = 100
while their registration_status is still Ongoing / New and no
actual_completion date is filed. Per RERA, a project is only formally complete when
status = Completed OR actual_completion is set. So we cap such projects at
99% for averaging. Capped rows below are marked
CAPPED.
seemankan1.projects.completion_percent · Excludes projects with NULL completion.
| Project | RERA | Status | Reported | Effective % |
|---|---|---|---|---|
| SHRI SAI CITY (PHASE-3) | PCGRERA281118000856 |
Ongoing | 100% | CAPPED 99% |
| sai city | PCGRERA150618000203 |
Ongoing | 90% | 90% |
| SUM ÷ COUNT | 189 ÷ 2 = 95% | |||
proposed_completion < today (23 Apr 2026)registration_status ≠ Completed AND actual_completion is NULL/emptycompletion_percent is intentionally not used here because RERA developers
self-report 100% even while the project is still Ongoing. Only the formal status / actual completion
date proves the project is closed.
| Project | RERA | Status | Proposed Completion | Completion % | Days Overdue |
|---|---|---|---|---|---|
| sai city | PCGRERA150618000203 |
Ongoing | 31 Dec 2019 | 90% | 2,305 d |
| SHRI SAI CITY (PHASE-3) | PCGRERA281118000856 |
Ongoing | 14 Aug 2024 | 100% | 617 d |