Diversity grouped from RERA project_type. Sell-through, completion %, delays and upcoming handovers
derived from total_units, units_sold, completion_percent,
proposed_completion & actual_completion across all merged promoter entities.
| Project | RERA Reg | Status | District | Area | Map | Website |
|---|---|---|---|---|---|---|
| vip city, sector - 01 | PCGRERA230618000310 |
Ongoing | Raipur | - | Map | Visit |
| VIP CITY, SECTOR -02 | PCGRERA270618000353 |
Ongoing | Raipur | - | Map | Visit |
| VIP CITY, SECTOR -03 | PCGRERA090718000503 |
Ongoing | Raipur | - | Map | Visit |
| VIP CITY, SECTOR -04 | PCGRERA260618000330 |
Ongoing | Raipur | - | Map | Visit |
| # | Complaint No. | Applicant | Section | Date | |
|---|---|---|---|---|---|
| 1 | M-ALL-2024-02476 | MR. PURNA CHANDRA SAHA | Section 11,Section 14 | 20 Jan 2025 | |
| 2 | M-PRO-2024-02455 | SMT. NEETA KURRE | Section 11,Section 14 | 20 Jan 2025 | |
| 3 | M-PRO-2024-02454 | MR. LAKHAN LAL HALDKAR | Section 11,Section 14 | 20 Jan 2025 | |
| 4 | M-PRO-2024-02453 | SMT. SURDHARA NAYAK | Section 11,Section 14 | 20 Jan 2025 |
| Factor | How it's calculated | Raw Value | Score (0-100) | Weight | Weighted |
|---|---|---|---|---|---|
| Builder-Level RERA Compliance Score | 4 project(s): 3 Compliant(100), 1 Partial(50) | 87.5/100 |
88
|
60% | 52.5 |
| Orders & Violations | 4 order(s) under 1 distinct RERA section(s). Score = max(0, 100 - 1 x 4) = 96 | 1 section(s) |
96
|
40% | 38.4 |
| Complaints Filed | 4 complaint(s) total. Only complaints with actual orders affect the score (via "Orders & Violations" factor above). | 4 | Info only — not scored | ||
| Buyer Rating | Average buyer review rating across all projects by this builder. | No reviews | Info only — not scored | ||
| Order Details | |||||
| Weighted Sum / Total Weight | 100% | 90.9 | |||
| Final Normalized Score | 91/100 | ||||
Avg. Completion % = SUM(effective_completion) / COUNT(projects with completion_percent NOT NULL)
completion_percent = 100
while their registration_status is still Ongoing / New and no
actual_completion date is filed. Per RERA, a project is only formally complete when
status = Completed OR actual_completion is set. So we cap such projects at
99% for averaging. Capped rows below are marked
CAPPED.
seemankan1.projects.completion_percent · Excludes projects with NULL completion.
| Project | RERA | Status | Reported | Effective % |
|---|---|---|---|---|
| vip city, sector - 01 | PCGRERA230618000310 |
Ongoing | 100% | CAPPED 99% |
| VIP CITY, SECTOR -02 | PCGRERA270618000353 |
Ongoing | 100% | CAPPED 99% |
| VIP CITY, SECTOR -03 | PCGRERA090718000503 |
Ongoing | 100% | CAPPED 99% |
| VIP CITY, SECTOR -04 | PCGRERA260618000330 |
Ongoing | 99% | 99% |
| SUM ÷ COUNT | 396 ÷ 4 = 99% | |||
proposed_completion < today (26 Apr 2026)registration_status ≠ Completed AND actual_completion is NULL/emptycompletion_percent is intentionally not used here because RERA developers
self-report 100% even while the project is still Ongoing. Only the formal status / actual completion
date proves the project is closed.
| Project | RERA | Status | Proposed Completion | Completion % | Days Overdue |
|---|---|---|---|---|---|
| VIP CITY, SECTOR -03 | PCGRERA090718000503 |
Ongoing | 30 Dec 2024 | 100% | 482 d |
proposed_completion between today and 26 Apr 2028actual_completion)| Project | RERA | Status | Proposed Completion | Completion % | Days Remaining |
|---|---|---|---|---|---|
| VIP CITY, SECTOR -04 | PCGRERA260618000330 |
Ongoing | 30 Apr 2026 | 99% | 4 d |
| vip city, sector - 01 | PCGRERA230618000310 |
Ongoing | 30 Dec 2026 | 100% | 248 d |
| VIP CITY, SECTOR -02 | PCGRERA270618000353 |
Ongoing | 30 Dec 2026 | 100% | 248 d |