Diversity grouped from RERA project_type. Sell-through, completion %, delays and upcoming handovers
derived from total_units, units_sold, completion_percent,
proposed_completion & actual_completion across all merged promoter entities.
| # | Complaint No. | Applicant | Section | Date | |
|---|---|---|---|---|---|
| 1 | SM-EXP-2024-02290 | CG-RERA | - | 10 Jun 2024 |
| Factor | How it's calculated | Raw Value | Score (0-100) | Weight | Weighted |
|---|---|---|---|---|---|
| Builder-Level RERA Compliance Score | 34 project(s): 29 Compliant(100), 5 Partial(50) | 92.6/100 |
93
|
60% | 55.6 |
| Complaints Filed | No complaints filed against this builder. | 0 | Info only — not scored | ||
| Buyer Rating | Average buyer review rating across all projects by this builder. | No reviews | Info only — not scored | ||
| Weighted Sum / Total Weight | 60% | 55.6 | |||
| Final Normalized Score | 93/100 | ||||
Avg. Completion % = SUM(effective_completion) / COUNT(projects with completion_percent NOT NULL)
completion_percent = 100
while their registration_status is still Ongoing / New and no
actual_completion date is filed. Per RERA, a project is only formally complete when
status = Completed OR actual_completion is set. So we cap such projects at
99% for averaging. Capped rows below are marked
CAPPED.
seemankan1.projects.completion_percent · Excludes projects with NULL completion.
| Project | RERA | Status | Reported | Effective % |
|---|---|---|---|---|
| pmay at (1232 dus) ashok nagar chantidih bilaspur (c.g.) | PCGRERA250322001357 |
Ongoing | 100% | CAPPED 99% |
| pmay at (406dus) madhuban bilaspur | PCGRERA250322001369 |
Ongoing | 100% | CAPPED 99% |
| PMAY AT INDRA VIHAR (256DUS) NUTAN CHOWK BILASPUR | PCGRERA250322001371 |
Ongoing | 100% | CAPPED 99% |
| pmay(29 dus) Ashok nagar sarkanda billaspur | PCGRERA250322001366 |
Ongoing | 95% | 95% |
| pmay at (87 dus) raj kishor nagar mopka bilaspur | PCGRERA250322001359 |
Ongoing | 89% | 89% |
| pmay (87 dus) at bandhwapara bilaspur | PCGRERA250322001356 |
Ongoing | 84% | 84% |
| pmay at rama green city (145 dus) khamtarai bilaspur | PCGRERA250322001361 |
Ongoing | 72% | 72% |
| PMAY AT CHINGRAJPARA (174 DUS) BILASPUR | PCGRERA250322001372 |
Ongoing | 66% | 66% |
| pmay at (87dus) imlibhatta sarkanda bilaspur | PCGRERA250322001370 |
Ongoing | 40% | 40% |
| pmay at (580dus) sakri, bilapur | PCGRERA290722001487 |
Ongoing | 32% | 32% |
| PMAY AT CHANTIDIH (319 DUS) BILASPUR | PCGRERA250322001360 |
Ongoing | 32% | 32% |
| pmay at 87 dus uslapur ,bilaspur | PCGRERA280222001350 |
Ongoing | 25% | 25% |
| pmay (58dus) behatarai, bilaspur | PCGRERA250322001355 |
Ongoing | 19% | 19% |
| pmay at abhishek nagar colony (44Dus)mangla bilaspur | PCGRERA250322001368 |
Ongoing | 8% | 8% |
| pmay at om space colony-1 (29 dus) sakri bilaspur | PCGRERA250322001364 |
Ongoing | 8% | 8% |
| PMAY FOR 58 DUS AB CALSTLE COLONY AMERI BILASPUR | PCGRERA290722001489 |
Ongoing | 5% | 5% |
| pmay at minibasti (1160dus) bilaspur | PCGRERA290722001486 |
Ongoing | 0% | 0% |
| pmay at mitti tila (261 dus) kududand bilaspur | PCGRERA280222001349 |
Ongoing | 0% | 0% |
| PMAY AT PUMPHOUSE (290 DUS) KUDUDAND BILASPUR | PCGRERA290722001490 |
Ongoing | 0% | 0% |
| SUM ÷ COUNT | 872 ÷ 19 = 46% | |||
proposed_completion < today (23 Apr 2026)registration_status ≠ Completed AND actual_completion is NULL/emptycompletion_percent is intentionally not used here because RERA developers
self-report 100% even while the project is still Ongoing. Only the formal status / actual completion
date proves the project is closed.
| Project | RERA | Status | Proposed Completion | Completion % | Days Overdue |
|---|---|---|---|---|---|
| pmay at (1232 dus) ashok nagar chantidih bilaspur (c.g.) | PCGRERA250322001357 |
Ongoing | 29 May 2022 | 100% | 1,425 d |
| pmay at mitti tila (261 dus) kududand bilaspur | PCGRERA280222001349 |
Ongoing | 27 Jun 2024 | 0% | 665 d |
| pmay at rama green city (145 dus) khamtarai bilaspur | PCGRERA250322001361 |
Ongoing | 04 Jun 2025 | 72% | 323 d |
| PMAY AT CHANTIDIH (319 DUS) BILASPUR | PCGRERA250322001360 |
Ongoing | 19 Jun 2025 | 32% | 308 d |
| pmay at (725 dus) Minimata bilaspur (c.g.) | PCGRERA250322001358 |
Ongoing | 28 Jun 2025 | 0% | 299 d |
proposed_completion between today and 23 Apr 2028actual_completion)| Project | RERA | Status | Proposed Completion | Completion % | Days Remaining |
|---|---|---|---|---|---|
| pmay (58dus) behatarai, bilaspur | PCGRERA250322001355 |
Ongoing | 28 Jul 2026 | 19% | 96 d |
| pmay at (87 dus) raj kishor nagar mopka bilaspur | PCGRERA250322001359 |
Ongoing | 12 Oct 2026 | 89% | 172 d |
| pmay at 87 dus uslapur ,bilaspur | PCGRERA280222001350 |
Ongoing | 07 Feb 2027 | 25% | 290 d |
| pmay (87 dus) at bandhwapara bilaspur | PCGRERA250322001356 |
Ongoing | 08 Feb 2027 | 84% | 291 d |
| pmay at (406dus) madhuban bilaspur | PCGRERA250322001369 |
Ongoing | 15 Mar 2027 | 100% | 326 d |
| pmay at (87dus) imlibhatta sarkanda bilaspur | PCGRERA250322001370 |
Ongoing | 15 Mar 2027 | 40% | 326 d |
| pmay at abhishek nagar colony (44Dus)mangla bilaspur | PCGRERA250322001368 |
Ongoing | 15 Mar 2027 | 8% | 326 d |
| pmay at abhishek vihar colony phase-1 & 3 (87 dus) mangla bilaspur | PCGRERA250322001365 |
Ongoing | 15 Mar 2027 | 0% | 326 d |
| PMAY AT CHINGRAJPARA (174 DUS) BILASPUR | PCGRERA250322001372 |
Ongoing | 15 Mar 2027 | 66% | 326 d |
| PMAY AT INDRA VIHAR (256DUS) NUTAN CHOWK BILASPUR | PCGRERA250322001371 |
Ongoing | 15 Mar 2027 | 100% | 326 d |
| pmay at om space colony-1 (29 dus) sakri bilaspur | PCGRERA250322001364 |
Ongoing | 15 Mar 2027 | 8% | 326 d |
| PMAY AT RAMAPURAM COLONY(58Dus) CHILHATI ,BILASPUR | PCGRERA250322001367 |
Ongoing | 15 Mar 2027 | 0% | 326 d |
| pmay(29 dus) Ashok nagar sarkanda billaspur | PCGRERA250322001366 |
Ongoing | 15 Mar 2027 | 95% | 326 d |
| PMAY FOR 116(DUS) SHIVAM VIHAR COLONY KHAMTARAI BILASPUR | PCGRERA170622001440 |
New | 11 Apr 2027 | 0% | 353 d |
| PMAY AT GARDEN CITY COLONY (58 DUS) AT MOPKA BILASPUR | PCGRERA010722001456 |
Ongoing | 02 Jun 2027 | 0% | 405 d |
| pmay at geetanjali city colony (58dus) uslapur ,bilapur | PCGRERA010722001463 |
Ongoing | 02 Jun 2027 | 0% | 405 d |
| PMAY AT KALYAN BAGH COLONY (145 DUS) AT RAJKISHOR NAGAR ,MOPKA ,BILASPUR | PCGRERA010722001457 |
Ongoing | 02 Jun 2027 | 0% | 405 d |
| pmay at sanjay city colony (116 dus) chilhati ,bilaspur | PCGRERA010722001460 |
Ongoing | 02 Jun 2027 | 0% | 405 d |
| pmay for 174(dus) at press club samiti ,birkona bilaspur | PCGRERA170622001438 |
New | 02 Jun 2027 | 0% | 405 d |
| pmay for 72(dus) M.P.GRIH NIRMAN SAMITI USLAPUR ,BILASPUR | PCGRERA170622001439 |
New | 02 Jun 2027 | 0% | 405 d |
| PMAY FOR GEETANJALI PARK COLONY (29 DUS) AT MANGLA ,BILASPUR | PCGRERA010722001458 |
Ongoing | 02 Jun 2027 | 0% | 405 d |
| PMAY FOR INDU GRDEN COLONY (87 DUS) AMERI ,BILASPUR | PCGRERA010722001459 |
Ongoing | 02 Jun 2027 | 0% | 405 d |
| PMAY FOR OM SPACE COLONY PHASE-2 (58 Dus) SAKRI BILASPUR | PCGRERA010722001455 |
Ongoing | 02 Jun 2027 | 0% | 405 d |
| pmay at (580dus) sakri, bilapur | PCGRERA290722001487 |
Ongoing | 19 Jul 2027 | 32% | 452 d |
| pmay at mahaveer city colony (232 dus) rajkishor nagar bilaspur | PCGRERA040822001501 |
Ongoing | 19 Jul 2027 | 0% | 452 d |
| pmay at minibasti (1160dus) bilaspur | PCGRERA290722001486 |
Ongoing | 19 Jul 2027 | 0% | 452 d |
| PMAY AT PUMPHOUSE (290 DUS) KUDUDAND BILASPUR | PCGRERA290722001490 |
Ongoing | 19 Jul 2027 | 0% | 452 d |
| pmay at talapara (261 dus) bilaspur | PCGRERA290722001488 |
Ongoing | 19 Jul 2027 | 0% | 452 d |
| PMAY FOR 58 DUS AB CALSTLE COLONY AMERI BILASPUR | PCGRERA290722001489 |
Ongoing | 19 Jul 2027 | 5% | 452 d |